May 20, 2025

Transmission Line

Stringing of wolf conductors in S/C 33kV Transmission Line
May 20, 2025

Transmission Line erected

Four Pole Strcucture of D/C 33kV Transmission Line erected by M/s Abhiraj Engineers
May 20, 2025

Transmission Line erected

Four Pole Strcucture of D/C 33kV Transmission Line erected by M/s Abhiraj Engineers
May 20, 2025

Constructed by M/s Abhiraj Engineers

6 X 33kV Transmission Lines from 132kV GSS to Various Distribution S/s, Total line lenght – Approx. 70Km
May 20, 2025

Constructed by M/s Abhiraj Engineers

1 X 33kV Bay Extension at, 33/11kV Sub-station at Tikrikilla, Meghalaya
May 20, 2025

Constructed by M/s Abhiraj Engineers

1 X 5 MVA, 33/11kV Sub-station at Rakshambre, Meghalaya
May 20, 2025

CGL Make Power Transformer erected and commissioned by M/s Abhiraj Engineers

Current Status: Charged and under gainful operations since 12-08-2023. Minor balance civil works is under Progress
May 20, 2025

M/s NECCON, POWERGRID and MeSEB

M/s NECCON, POWERGRID and MeSEB officials during commissioning of 50MVA Power X-Mer
May 20, 2025

Control Room Building

655Sqmtr. Control Room Building constructed by M/s Abhiraj Engineers